New library construction timeline
Our new library opened January 6, 2008.
- August 15, 2005 – Work on the new south entrance and temporary south parking lot started
- September 1, 2005 - Groundbreaking Celebration more
- November 1, 2005 – New south entrance, parking lot opened
- November 2005 – Construction of the new library began
- January 2006 – Auditorium removed
- December 9, 2007 – Last day of service in old library
- Mid-December, 2007 – Demolition of old library starts
- January 6, 2008 – New library opens
- Summer 2008 – Completion of the final steps, removing the old library, then finishing the parking lot and landscaping